Hello ,
tender documents OBLIGATION to carry out plans under REVIT
start of construction half of the parts are under Autocad
file of executed works request today under DWG charter
(Imposed blocks, limited color name layers "no hidden object", geolocation)
DOE of course to work on a basic background plan outside the graphic charter
Hello Stéphane,


If it is a public contract then the contracting authority is subject to the fundamental principles of public procurement (equal treatment, freedom of access and transparency of procedures)

As such, the MOA must respect the principle of equal treatment of candidates for the award of a public order contract. It implements the principles of freedom of access and transparency of procedures, under the conditions defined in this code. This new wording prioritizes the principle of equal treatment of candidates over the other two.

As a result, computer formats such as product references must meet these fundamental criteria. Here is a document dealing with the
DEMATERIALIZATION OF PUBLIC PROCUREMENT

If it is a private market then there is in my humble opinion no restriction as to the methods and formats or product references to be used or returned.


Christophe Fortineau
Consultant, trainer and AMO BIM
there 3 days
·
#16585
0
Votes
Cancel
Hello,
I have known similar situations ... And that's a shame.
Sincerely
Sarah
there 3 days
·
#16589
1
Votes
Cancel
to put it into perspective, here is an operator's point of view:

the ideal is a BIM DOE, with the well-informed and up-to-date BIM model, TQC,

otherwise, it is better to receive an up-to-date digital DOE than an outdated BIM model,

otherwise, it is better to have an up-to-date paper DOE than an outdated digital DOE,

otherwise, it is better to have an EXE file than an outdated DOE, because at least we know that it is not a DOE.
There is no response to this discussion yet.
Be the first to answer it!
Do you have any questions?

Need technical support, advice or advice?


Discover Hexabim services

recruitment

Your career at N&Co

Find out more

Advertising

Advertising

Find out more

communication

Communication

Find out more

Hexabim

Log in

The Cron starts